Currently, the project is in both the Design and Construction Phase. Some current activities include:
- Finalizing details for the bridges
- Reviews of design plans by multiple agencies to insure all requirements are met
- Coordination with existing utilities to relocate any necessary conflicts with the new proposal
- Test piles are being driven to obtain data
- Production piles are being driven at some locations
- Earthwork north of the Hillsboro Canal.
Anticipated Construction Activities for the month of September 2010:
- Production Piles to be driven during daytime hours
- Earthwork operations to grade soil to the proper density and elevation North of the Hillsboro Canal.
- Drainage pipe and structure installation on Dixie Hwy North and South of the Hillsboro Canal.
- Roadway widening on Eastbound Hillsboro Blvd.
Estimated Construction Complete Summer 2012