PROJECT NEWS

No current project News updates at this time.

 
UPCOMING CLOSURES

As of September 7th, 2010, there will be a sigle lane closure for Eastbound Hillsboro Blvd. approaching Dixie Highway for roadway widening work.  The lane closure will be from the hours of 9am to 4pm.  Please use caution when driving through this area.

 As of September 7th, 2010, there will be a sigle lane traffic on North River Ave. for new drainage installation work.  The lane closure will be from the hours of 9am to 4pm and  Please use caution when driving through this area.

 
TRAFFIC UPDATE

Currently, there are no traffic issues to report on the project.

 
SEARCH

WANTMAN GROUP LOGO

Wantman Group, Inc. (WGI) is a multidisciplinary consulting firm headquartered in West Palm Beach, Florida with a 35-year history specializing in engineering, planning, surveying and mapping, and environmental services. The firm is comprised of eight separate divisions devoted to the following disciplines: Civil Engineering, Municipal, Transportation, Surveying, Subsurface Utility Engineering, Construction, Environmental, and Planning Services. The firm derives all of its revenue from Florida-based clients and remains dedicated to the development and economic prosperity of the local communities. During the last decade alone, the firm has provided professional services on hundreds of projects, encompassing thousands of acres of land and in the excess of $500 million in development and infrastructure costs. WGI’s qualifications in civil engineering, surv eying, and associated permitting has resulted in numerous repeat clients, many of whom date their past projects with WGI to over 30 years ago.

Wantman Group Truck
Conr Graham Logo

 

 
CONSTRUCTION PROGRESS

As of 8/15/2010:

% Contract Budget Expended = 27%

% Contract Time Used = 27%

 
CONSTRUCTION SCHEDULE

Antipated Schedule:

Completion of Pile Driving/Foundations - Fall/Winter 2010

Completion of Hillsboro FEC Rail Road crossing - Fall/Winter 2010

Completion of the 2nd Ave Ramp Bridge - Winter 2010/2011

Estimated Construction Complete Summer 2012.

Please see the Schedule Tab for more details.

 
CURRENT WORK

Anticipated work for the month of September 2010:

  • Continuation of Pile Driving for the Mainline Dixie and 2nd Ave. Ramp Bridges.
  • Continuation of Drainage pipe and Drainage structures.
  • Continuation of Earthwork north of the Hillsboro Canal.
  • Start of roadway widening on Hillsboro Blvd.
  • Continual maintenance of Storm Water Pollution Prevention Devices.
  • Continual maintenance of Traffic Control Devices.
 