PROJECT NEWS

Dixie fly-over deck pours are 100% complete.

Pedestrian bridge steel tub has been placed.

Sidewalks and barrier walls construction on the Dixie fly-over are nearing completion.

 
UPCOMING CLOSURES

There are no anticipated closures related to this project at this time.

 
TRAFFIC UPDATE

Motorists are advised to exert full caution during the new traffic pattern. Please follow all traffic regulations such as remember to come to a complete stop at all stop signs. Safety is our priority; please notify us always of any concerns or suggestions that you may have in order to continue providing you with a safe commute.

 

 

 
SEARCH

PostHeaderIcon GALLERY - Progress Pictures

Category List
dixie may aerial1
dixie may aeria...
Image Detail
dixie may aerial2
dixie may aeria...
Image Detail
dixie may aerial3
dixie may aeria...
Image Detail
pile driving
pile driving
Image Detail
cleared1
cleared1
Image Detail
cleared2
cleared2
Image Detail
cleared3
cleared3
Image Detail
cleared4
cleared4
Image Detail
june aerials1
june aerials1
Image Detail
june aerials2
june aerials2
Image Detail
june aerials3
june aerials3
Image Detail
rainbow
rainbow
Image Detail

 

Display Num 
 
 
Powered by Phoca Gallery
CONSTRUCTION PROGRESS

As of 1/03/2012:

% Contract Budget Expended = 94%

% Contract Time Used = 78%

 
CONSTRUCTION SCHEDULE

Anticipated Schedule:

Dixie Flyover open to traffic- February 2012

Complete construction of pedestrian bridge - March 2012

Estimated Construction Complete Early Summer 2012.

Please see the Schedule Tab for more details.

 
CURRENT WORK

Anticipated work for the month of January to March 2012:

  • Dixie Flyover approach slab and expansion joint pours
  • Pedestrian railing and fence placement
  • Pedestrian Bridge Deck pour
  • Continual maintenance of Storm Water Pollution Prevention Devices.
  • Continual maintenance of Traffic Control Devices.
 