Dixie fly-over deck pours are 100% complete. Pedestrian bridge steel tub has been placed. Sidewalks and barrier walls construction on the Dixie fly-over are nearing completion. |
|
There are no anticipated closures related to this project at this time. |
|
Motorists are advised to exert full caution during the new traffic pattern. Please follow all traffic regulations such as remember to come to a complete stop at all stop signs. Safety is our priority; please notify us always of any concerns or suggestions that you may have in order to continue providing you with a safe commute.
|
|
As of 1/03/2012: % Contract Budget Expended = 94% % Contract Time Used = 78% |
|
Anticipated Schedule: Dixie Flyover open to traffic- February 2012 Complete construction of pedestrian bridge - March 2012 Estimated Construction Complete Early Summer 2012. Please see the Schedule Tab for more details. |
|
Anticipated work for the month of January to March 2012:
|
|
|