PROJECT NEWS

Dixie fly-over deck pours are 100% complete.

Pedestrian bridge steel tub has been placed.

Sidewalks and barrier walls construction on the Dixie fly-over are nearing completion.

 
UPCOMING CLOSURES

There are no anticipated closures related to this project at this time.

 
TRAFFIC UPDATE

Motorists are advised to exert full caution during the new traffic pattern. Please follow all traffic regulations such as remember to come to a complete stop at all stop signs. Safety is our priority; please notify us always of any concerns or suggestions that you may have in order to continue providing you with a safe commute.

 

 

 
SEARCH

Dixie Highway Project
Frequently Asked Questions


1. Question: What is the purpose of this project?

Answer: The purpose of the Dixie Highway Flyover Project is to improve capacity and safety for the traveling public along Dixie Highway by eliminating the crossing at the FEC Railroad as well as the intersection with NE 2nd St. The project will also provide direct access to Pioneer Park for the public traveling southbound along Dixie Highway. The project will improve aesthetics, lighting, drainage, and landscaping to the Cities of Deerfield Beach and Boca Raton.

2. Question:
When is the project going to begin?

Answer: The Design portion of the contract is currently underway.  Construction is also currently underway and began Mid March 2010.

3. Question:
When will the project finish?

Answer: The project is currently scheduled to finish in the Summer of 2012.

4. Question: How much does the project cost?

Answer: Design and Construction costs for the project total $39,525,385.00.

5. Question: How is the project being funded?

Answer: This project is being funded through The American Recovery and Reinvestment Act (ARRA) of 2009, also referred to as the Federal Economic Stimulus.  Through ARRA funds, Broward County was able to fully fund this project.  For more infomation on how The Florida Department of Transportation is using the ARRA funding statewide, please visit http://www.dot.state.fl.us/planning/economicstimulus/.

6. Question: Will I be able to drive, bike, and walk through the construction project limits?

Answer: Yes, throughout the life of the project, the public will be able to drive through the project limits.  Access will also be maintained for pedestrians and bicyclists during the project.  Please observe and adhere to all posted construction signs during the project.

7. Question: How can I get more information regarding this project?

Answer: At the top of this website, there is a contact us tab that provides you with an opportunity to contact us regarding questions on the project.  Our Project Management Team appreciates your comments, and will respond to you in a timely manner.

 

 
CONSTRUCTION PROGRESS

As of 1/03/2012:

% Contract Budget Expended = 94%

% Contract Time Used = 78%

 
CONSTRUCTION SCHEDULE

Anticipated Schedule:

Dixie Flyover open to traffic- February 2012

Complete construction of pedestrian bridge - March 2012

Estimated Construction Complete Early Summer 2012.

Please see the Schedule Tab for more details.

 
CURRENT WORK

Anticipated work for the month of January to March 2012:

  • Dixie Flyover approach slab and expansion joint pours
  • Pedestrian railing and fence placement
  • Pedestrian Bridge Deck pour
  • Continual maintenance of Storm Water Pollution Prevention Devices.
  • Continual maintenance of Traffic Control Devices.
 