PROJECT NEWS

A Groundbreaking Ceremony was held on 4/16/2010 at 11am.  This ceremony was for the Florida Department of Transportation, it's partners and the public to come together to celebrate the begining of the Dixie Flyover Project.  Thank you to everyone who helped out with the ceremony and thank you to everyone who joined us in the celebaration.

 
UPCOMING CLOSURES

As of June 29th, 2010 there is a single lane closure on Dixie Highway Northbound north of the Hillsboro Canal.  Please use caution when driving through this area.

 

 
TRAFFIC UPDATE

Currently, there are no traffic issues to report on the project.

 
SEARCH


Dixie Flyover Rendering

This project involves the realignment of Dixie Highway from south of Hillsboro Boulevard (SR-810) to north of the Hillsboro Canal. Just north of the Hillsboro Boulevard intersection, the proposed 4-lane alignment raises vertically and becomes an elevated structure over NE 2nd Street, NE 1st Avenue, North River Avenue, Florida East Coast (FEC) Railway tracks, NE 2nd Avenue, and the Hillsboro Canal. Once the elevated structure crosses over the Hillsboro Canal and enters Palm Beach County, the alignment ties back down to the existing roadway. By eliminating an at-grade FEC Railway crossing, the new flyover will reduce travel times and decrease conflict points along the route, thereby providing local motorists and pedestrians with a safer route to downtown Deerfield Beach and the amenities of Pioneer Park.

* The rendering above is for general information only and does not show all details and is not to scale

Read more about

 
CONSTRUCTION PROGRESS

As of 6/13/2010:

% Contract Budget Expended = 24%

% Contract Time Used = 20%

 
CONSTRUCTION SCHEDULE

Pavement and Drainage work at Dixie Hwy and Hillsboro Blvd. has started 6/14/2010.

Production Pile Driving for the bridge has started 6/14/2010.

Ground Breaking Ceremony was held on 4/16/2010.

Estimated Construction Complete Summer 2012.

Please see the Schedule Tab for more details.

 
CURRENT WORK

Pavement and Drainage work began mid-June near the intersecdtion of Dixie Hwy and Hillsboro Blvd.  This work is needed to accomodate the roadway alignment changes.

Pile driving began in Mid-March.  Several test piles will be driven to determine the depth at which all the remaining piles will need to be driven to meet the capacity for the bridges. 

 

Broward County Seal

Deerfield Beach Seal

Palm Beach County Seal